- 1. Assembly of funnel formwork (supporting steel skeleton).
- 2. Continuous concrete work, optimum compacting, maximum concrete drop 50cm.
- 3. Dismantled funnel.
- 4. Cylinder: Exterior formwork set up, reinforcement for the first construction phase installed, interior formwork is raised.
- 5. Spacers for the self-supporting formwork are installed and the formwork is ready for concrete work.
- 3. Exterior formwork raised after concrete work.
- 7. Exterior formwork with special buttress design.
- 8. Hanging scaffolding for opening and closing the exterior formwork.
- 9. Assembling the support ring for the conical roof formwork.
- 10. Assembling the support ring for the conical roof formwork.
- 11. Supporting steel structure of the conical roof formwork assembled.
- 12. Placement of wooden formwork skin.
- 13. Reinforcement.
- 14. Assembly of the exterior formwork for the cone (detail: curved transition piece).
- 15. Continuous concrete work, optimum compacting, maximum concrete drop 50cm.
- 16. Disassembling the exterior formwork.